|
|
|
IntroductionImportance of the Public Investment Programme (PIP)
Within
the framework of its policy of liberalisation of the economy and the
conclusion of the Enhanced Structural Adjustment Facility (ESAF) with the
Bretton Woods institutions in 1998, the Government is reducing its role in
direct productive activities and most of the public enterprises are being
privatised. However, there is still need for the Government to plan its own
activities, particularly when the private sector is not yet well developed
and the Government is still the main initiator and investor in the country. Consistency of the
PIP with National Economic Policy
Consistency of Programmes and Projects with Sectoral Policy
The
PIP 1999-2001 adopts a ‘Programme Approach’. The sectoral programmes
were identified from the sectoral strategies, which themselves emanated from
the sectoral objectives. The projects in the PIP were in turn identified
from the programmes. This programme approach is an important part of the
selection and prioritisation process which helps to ensure that the scarce
resources available are devoted to programmes and projects which are in tune
with national and sectoral objectives, policies and strategies. Projects
earmarked for the PIP were screened against the programmes according to
project screening critieria (see main document Chapter 10 p.63 for a list of
these).
The process of the
preparing the PIP 1999-2001 document
The process of preparing PIP
involved the following steps :
To
improve the process of preparing the PIP, the following actions must be
taken :
Government
Objectives and Macroeconomic Policy
See
the Policy Framework Paper. Sector
Objectives and Policies for the Period 1999-2001
The
sectoral policies and strategies allow among other things :
The
allocation of the resources of the PIP must be coherent with sectoral
objectives, policies, strategies and programmes. The policies are defined
from objectives and strategies from policies. Subsector programmes are also
defined from strategies. Part II of the main PIP document indicates the
objectives, policies, strategies and priority programmes. The sector policies and strategies have been defined by sub-sector. These sub-sectors are grouped into specific sectors, which in turn are grouped into the four major sectors as follows:
Summary
of Investment Expenditure Status from 1996 to 1998
The investment expenditure for the years 1996, 1997 and 1998 (127,718.48 millions FRW) were realised at a rate of 48.47%. In 1996, the realisations were valued at 33,303.15 millions FRW or 43.02% of the provisional estimates of 77,418.58 millions FRW. In 1997 they amounted to 46,054.24 millions FRW for the estimated 108,343.61 millions or a rate of realisation of 42.51%. In 1998 the amount of realisations was 48,361.11 or 62,21% of the provisional estimates of 77,743.52 millions. Sectoral breakdown of
expenditure from 1996 to 1998
The sectors of Human Resources and Social Development, Infrastructures and Administration and Finance registered high expenditure during the period, with 39,92%, 22,85% and 21,02% respectively, of the total expenditure. In comparison to what had been planned initially, it was the sectors Administration and Finance and Human Resources and Social Development that achieved the highest performance, at a rate of 68,10% in Administration and Finance, and 55,71% in Human Resources and Social Development. Table 1: Sectoral breakdown of
investment expenditure from 1996 to 1998 (in
millions of RwF)
The weak performance of the Productive sector as well as the Infrastructure sector is due essentially to delays in the starting up of projects. These are caused firstly by difficulties in fulfilling implementation conditions of credit agreements or financing conventions, secondly by the complexity of donor procedures and especially modalities of tenders and fund disbursements. Some projects for which some funds were programmed have been closed before their end, and their funds have been allocated to other activities that were not necessarily realised : this is among others the case for the Energy Restructuring Project (PRSE), the Agricultural Services Project (PSA) etc… Graph 1: Sectoral breakdown of investment expenditure 1996 to 1998The low level of realisation (48,47%) is due several factors, including:
Analysis of Investment Expenditure Requirements of Ministries for the 1999-2001 PeriodIn conformity with the principle of
coherence between the Public Investment Programme and economic and financial
policies defined by the macroeconomic framework, the allocation of resources
to programmes and projects must respect the budgetary ceilings determined
according to financial constraints and sectoral policies. This chapter makes
an analysis of the total expenditure requirements for the years 2000 and
2001 as formulated by the line ministries before the Government reshuffle of
8 February 1999, and aims to show the distance between needs and available
resources. The investment needs expressed by the ministries amount to RwF 342,148.89 million, (or the equivalent of US$ 1,0793.33 million at an exchange rate of 317.0 RwF for 1 US$). They are spread over the three years as follows : RwF 71,700.01 million in 1999 i.e. 20.96% of the total amount ; RwF 149,985.26 million in 2000 i.e. 43.25% and RwF 122,463.62 million in 2001 i.e. 35.75%. The breakdown of requirements by ministry is contained in Table 5 of the main document of PIP. Sectoral analysis of expenditure requirements for the period 1999-2001
As shown in table 2 below, the Infrastructures sector requires the largest part of the resources and comes first in ranking with RwF 130,794.73 millions i.e. 38.23% of the total requirements. The Human Resources and Social Development sector should occupy the second rank with RwF 98,272.06 million or 28.72%; the Productive sector comes in third place with RwF 77,965.41 million or 22.79% of the global requirements, before Administration and Finance sector which should benefit from an allocation of RwF 35,116.69 million i.e. 10.26%. Table
2: Annual and sectoral breakdown of investment requirements for the period
1999/2001 (in million RwF)
Anaysis of the Financial Programming of the PIP 1999-2001 on the Basis of the ESAF CeilingsThe
requirements of the ministries have been adjusted to respect the ESAF
budgetary ceilings. Therefore, the programming of the financing being
negotiated has been postponed to 2000 and most of the financing to be sought
has been programmed from 2001 on. After these adjustments, the PIP 1999/2001 amounts to RwF 234,400.0 million (or the equivalent of US$ 739.43 million at an exchange rate of 1 US$ for 317.0 RwF), against RwF 226,037.41 million for the PIP 1998-2000. This ceiling encompasses 498 projects grouped into 106 sector programmes (see Annexes 6 and 7 in the main PIP document). It registers a slight increase of 3.7% in relation to the previous PIP. The total represents 10.51% of GDP over the 1999-2001 period, whereas the total of the PIP 1998-2000 represented 10.13% of estimated GDP for 1998-2000. Nature of the 1999-2001 PIP expenditures
The categorization of projects
according to the nature of expenses in Table 3 below, allows us to note that
76.34% of the 1999-2001 PIP expenditures may be considered as being
investments linked to the creation of gross fixed capital, while 13.49%
constitute recurrent expenditures, and the rest of 10.13% constitute
technical assistance and pre-investment expenditures. This categorization
remains a summary and should be further developed for the future PIPs in
order to determine with more precision what the real investment expenditures
are, and their implications in terms of recurrent costs which must be borne
by the recurrent budget. Table 3: Breakdown of expenditure estimates of the PIP 1999-2001 by nature of expenditure (in million RwF)
(TA = Technical Assistance, REC = Recurrent, INV = Investment, PRE = Pre-investment) Sector-based analysis of the 1999/2001 PIP expenditure estimatesIn accordance with the priorities
set out in the Policy Framework Paper for the Enhanced Structural Adjustment
Facility, high priority must be given to the sectors of agriculture and
infrastructure. Also, resources allocated to the human resources sector must
be substantially increased. In this perspective, while allocating resources
for the present PIP and especially for the years 2000 and 2001, a particular
attention has been given to health and education in order to increase the
resources of the Human Resources and Social Development sector. As shown in Table 4 below, the
sectoral breakdown of resource allocation under PIP 1999-2001 reflects the
top priority given to the sector of Human Resources and Social Development
with a share of RwF 82,452.75 million, representing 35.18% of the total
resources planned for the period under consideration. The Productive sector
comes second with RwF 64,256.68 million, or 27.41%, followed in third place
by the sector of Infrastructure with RwF 58,873.51million, or 25.12%, and
finally the sector of Finance and Administration, which is allocated RwF
28,817.06 million, or 12.29 % of the Programme’s resources. One notes that the adjustment of expenditure requirements allowed to contain the PIP amount 1999-2001 within the ESAF budgetary ceiling and to obtain a sector priority in conformity with the sector allocation recommended in the Policy Framework Paper. Table 4: Annual sectoral breakdown of PIP Expenditure 1999-2001 (in millions of RwF)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||